Supreme Petrochem Plans ₹450-Crore Second mABS Line With Versalis Technology, Doubling Planned Capacity to 140 KTPA

Singur Plant (Chemical factory) of Himadri Speciality Chemicals Limited in Hooghly district (18 June 2022) (file photo)
Photo: This photograph is created by Sbb1413. All photographs created by him are releas / Wikimedia Commons, CC BY 4.0 (file photo)

Supreme Petrochem Ltd has signed a technology agreement with Italy’s Versalis S.p.A. for a second 70 KTPA mass ABS (mABS) production line, an investment of about ₹450 crore that would take the company’s planned mABS capacity to 140 KTPA. The agreement was signed on 12 November 2026 and disclosed to the stock exchanges on 17 November under the SEBI listing regulations. Mechanical completion of the new line is targeted for December 2028.

Funded from internal accruals

According to reports on the disclosure, the company plans to fund the project entirely from internal accruals. Supreme Petrochem reported an investable surplus of ₹886 crore and zero debt as of 30 September 2026, which leaves room to finance the line without new borrowing. Reports noted that the company did not give a break-up of the ₹450 crore between technology, construction, utilities and other project costs.

The company cited growing demand for ABS products in India as the reason for the expansion.

Building on the first Raigad line

The new line builds on a relationship that dates back to December 2021, when Versalis agreed to license its mass ABS technology and provide basic engineering for a 70 KTY unit at Amdoshi-Wangani in Raigad district, Maharashtra. That first line was commissioned in September 2025. Coverage of the earlier deal described it as the first phase of a planned 140 KTA project, with a second line of the same size envisaged. The latest agreement puts that second phase on a firm footing.

Reports on the latest disclosure put utilisation of the existing 70 KTPA line at about 60%. That suggests the company is committing to new capacity well ahead of filling the first line, with a lead time of roughly two years before the second line is mechanically complete.

Why mass ABS matters

ABS (acrylonitrile butadiene styrene) is an engineering thermoplastic widely used in appliances, consumer electronics, automotive interiors and some piping and fittings applications. Mass polymerisation, the process licensed from Versalis, is an alternative to the more common emulsion route.

Supreme Petrochem is primarily known as a styrenics producer, and the mABS project extends its portfolio further into engineering plastics.

What it means for Indian processors

For moulders and compounders, an additional 70 KTPA of domestic ABS capacity from end-2028 means more local sourcing options, potentially shorter lead times and less exposure to freight and currency swings on imported grades. The two-year window gives buyers time to qualify grades from the first line, which is already running.

For the wider polymer industry, the decision shows Indian producers still committing capital to downstream and specialty polymers even as commodity polymer prices soften. Investors will watch how quickly utilisation at the first line rises before the second comes on stream.